LCA WEST PIER EXTENSION

London City Airport
Client: London City Airport (LCA)
Main Contractor: London City Airport (LCA)
Sector: Aviation
Steel: 380 te
Completed: 2015 – 2016
Location: London
Scope: Structural Steelwork
Cladding
Metal Decking
Services: Detailing
Connection Design
Fabrication
Site Installation
Keywords:
Vierendeel Steelwork
Offsite Intumescent
Cladding
Rainscreen Cladding
Glazing
Steel Doors

Project Summary

As part of a £16 million development programme to reconfigure London City Airport’s Western Pier, we supplied and installed the structural steel, metal decking, and cladding to form the new 300 metre-long extension to the existing Pier.

Comprising of a single storey structure with vierendeel glazing support steelwork to the length of the extension, the extension support increased the Pier footprint by over 80%, to support 70% of the airport’s departure gates.

In addition to the supply, fabrication, and installation of the structural steelwork, we provided offsite intumescent coating up to 60 minutes fire protection, along with 1600 square metres of Comflor 60 metal deck, 1,800 square metres of Roofdek D100 decking, and the full cladding envelope.

The staged install programme required airside deliveries and site installation in two phases, with limited site storage.